First mining farm with own small cascade of hydropower plant build by Watt Community.
Power output
Kirov Mining Farm is located in Talas region, Northwestern Kyrgyzstan. With an estimated power output of 15 MW, the mining hotel will be the first off-grid mining facility in Kyrgyzstan
Technology
Turbulent and Waterwheel type of hydro generators will be installed to generate electricity
Mining space
With a total area of 2000 square meters, the Kirov Mining Farm will be officially the largest mining farm in Kyrgyzstan
Timeline
Kirov Mining Farm
August - December 2021
August - December 2021
Design and planning
January - April 2022
January - April 2022
Installing Turbines on three main canals below the dam
May 2022
May 2022
Test of turbines, power output test
Determine the stable power output from cascade of turbines
Installing ASICs from Watt community's members and testing the cooling system for the farm